More than two thirds of Power of Siberia gas pipeline ready by early February — Gazprom

Главная » News » More than two thirds of Power of Siberia gas…

MOSCOW, Febuary 6. /TASS/. As of early February 2019, Russian energy giant Gazprom has already built 1480 kilometers, or two thirds of the Power of Siberia pipeline to transport Siberian gas to Russian Far East and China, a senior Gazprom manager told investors in New York on Tuesday.

“As of early February, we have already built 1,480 km, which makes more than two thirds of the stretch from the Chayandinskoye gas field to the Chinese border, needed to start gas deliveries to China,” Kirill Polous said.

“Only in 2017, we built more than 900 kilometers [of the pipeline], which is way ahead of schedule,” he added.

“At the moment, we keep working jointly with our Chinese partners on new pipeline projects,” the official said. “And we expect to occupy 13% of the Chinese gas market by 2035.”

Gazprom deputy CEO Alexander Medvedev said that “as soon as prices will be agreed, we will announce the start of deliveries.” “I’m sure that this time it will take a lot less time than before,” he added.

Deliveries to China

Currently, Gazprom is building the Power of Siberia gas pipeline, which will pump natural gas from the giant Chayanda oil and gas condensate deposit in Yakutia and the Kovykta gas condensate field in the Irkutsk Region in Eastern Siberia to deliver gas to the domestic market (via Khabarovsk to Vladivostok) and further on for exports to China. The pipe’s section aimed for China will be built near Blagoveshchensk. The eastern route stipulates the supply of 38 billion cubic meters of natural gas to China annually within 30 years. The value of the contract is estimated at $400 billion.

This year, Gazprom plans to invest 217.988 billion rubles in the project. In 2017, Gazprom investment in the Power of Siberia pipeline increased to 158.811 billion rubles ($2.7 bln) from 76.162 billion rubles ($1.3 bln).

The terms of the partnership in design, construction and operation of the cross-border zones of the gas pipeline are defined by an intergovernmental agreement dated October 13, 2014. The pipeline is expected to start delivering Russian gas to China on December 20, 2019.

In 2015, Gazprom and CNPC signed an agreement on the basic conditions of pipeline gas deliveries from Western Siberia to China via the “Western” route (Power of Siberia-2 pipeline). Initially supplies are envisaged at 30 billion cubic meters of gas per year. Also in 2015, Gazprom and CNPC signed a memorandum of understanding on the project of pipeline shipments of natural gas to China from Russia’s Far East.

Source: TASS

MORE

Gazprom’s Amur gas processing plant remains on schedule

Construction of the project’s main phase is progressing on schedule, with supply and assembly of Linde AG’s equipment for cryogenic gas separation installations of the complex’s first production lines now under way, with additional heavy equipment for those units to be shipped to the site via the Zeya River starting this summer, Gazprom said. The…


Saudi Arabia and Russia consider 10 to 20 year oil alliance

Russia and OPEC member Saudi Arabia are seeking to extend oil market cooperation for decades to stabilise crude prices. Saudi Arabia and Russia are working on a long-term deal to extend their alliance on oil curbs that began in January 2017, after a crash in crude prices. “We are working to shift from a year-to-year…


Russia, Saudi Arabia in talks for unprecedented deal to control oil supplies for 20 years

NEW YORK — Saudi Arabia and Russia are working on a historic long-term pact that could extend controls over world crude supplies by major exporters for many years to come. Saudi Crown Prince Mohammed bin Salman told Reuters that Riyadh and Moscow were considering a longer deal to extend a short-term alliance on oil curbs…


Spelling error report

The following text will be sent to our editors: